Foundations are In!
November 17, 2010Foundations for both 3 Bar G and First Up! are now in the ground and curing. Four weeks from today is the first opportunity to erect the turbines. Foundation installation had several small setbacks each making for a small delay … Read more…
Posted in Uncategorized | 2 CommentsFoundations Going In!!
November 3, 2010Steel and Concrete are in the ground and more a comin’! Though SNAFUs abound causing annoying delays (misdrilled holes, wrong parts delivered, unqualified inspector showing up on site, …) it is undeniable that turbines are in the process of going … Read more…